PMP Practice Questions
Project Management Professional (PMP) — Practice with free PMP sample questions and answers covering all three domains - People, Process, and Business Environment. Each question includes a detailed explanation to help you understand the reasoning, not just memorize answers.
Free Sample Questions
Here are 5 free sample questions from our full bank of 200+ PMP practice questions. Try them out below — click "Show Answer" to reveal the correct response and explanation.
You are managing a large infrastructure project and have just identified a key stakeholder who was overlooked during the initial stakeholder identification process. This stakeholder has significant influence over regulatory approvals. The project is already 30% complete. What should you do FIRST?
A project has five activities on the critical path: A (3 days), B (5 days), C (4 days), D (6 days), and E (2 days). Activity F (3 days) runs in parallel to activities C and D with a total float of 4 days. The project sponsor asks you to compress the schedule by 3 days. What is the BEST approach?
During project execution, a team member identifies a risk that could delay a critical deliverable by two weeks. The risk has a 40% probability of occurring. The estimated cost impact if it occurs is $50,000. The team proposes a mitigation strategy costing $15,000 that would reduce the probability to 10%. What is the expected monetary value (EMV) of the risk BEFORE mitigation?
You are leading a project where the customer's requirements are evolving rapidly, and the technology is relatively new to your team. The project sponsor wants a detailed, fixed-scope plan delivered upfront. What is the MOST appropriate response?
A project has a Budget at Completion (BAC) of $200,000. At the end of month 4, the Planned Value (PV) is $80,000, the Earned Value (EV) is $70,000, and the Actual Cost (AC) is $90,000. What do the Schedule Performance Index (SPI) and Cost Performance Index (CPI) tell you about this project?
Get the Full PMP Question Bank — 200+ Practice Questions
You just saw 5 sample questions. We have a complete bank of 200+ PMP practice questions with detailed answers and explanations ready for you. Fill out the form below and we'll send you the full question bank — completely free.
About the PMP
Format & Structure
- Total Questions
- 180
- Time Limit
- 230 minutes (3 hours 50 minutes)
- Format
- Multiple choice, multiple response, matching, hotspot, fill-in-the-blank
Scoring & Cost
- Passing Score
- Above/Target/Below Target (no fixed number)
- Registration Fee
- $405 (PMI member) / $555 (non-member)
Related Practice Questions
Frequently Asked Questions
How many questions are on the PMP exam?
What is the PMP passing score?
How hard is the PMP exam?
How much does the PMP exam cost?
What are the PMP eligibility requirements?
How long should I study for the PMP?
Is PMP certification worth it?
Get 200+ PMP Practice Questions
Don't settle for just 5 sample questions. Request the full question bank and start preparing with confidence.
Get Started